Professional Summary
A License Civil Engineer with total 13 years’ experience in both vertical and horizontal construction, performance driven in facilitating growth thru the implementation of project that fulfill the project requirements. A highly effective at managing, improving delivery and forecast of the additional project needs. A professional believes that proper execution, control, and coordination may lead the project into smooth and progressive production and thru this believes the complete knowledge and professionalism are necessary.
Area of Expertise: Building construction, Roads and Railways Construction, Real Estate and Subdivision.
License Civil Engineer
Project Involvement: Avida Settings Lipa Project ( Land Development Package )
Sicogon Island, Land Development Project
Avida Setting Vermosa Project ( Land Development Package )
Manage and lead the team to achieve the goal within a given budget and time. Provide the strategic plan for execution as well as how to monitor and control the project during the project implementation.
Project Involvement: Riyadh Metro Railway Project ( Line 3 )
Project implementation and supervision to ensure that sub – contractor’s activities are as per contract agreement. Reviewing site drawings for implementation and creating technical queries regarding some site issues, conflicts, and the difference in plans versus actual site situation. Managed the site to ensure that progress is on schedule by overlooking the possible conflict with the none predicted stakeholder/s. Preparing bar bending schedule for approval and prior to implementation.
Project Involvement: La Salle Antipolo Classroom and Laboratory
Responsible for overall project site planning, control, and execution. Managed the team to ensures that all team will work coordinated to each field of specialization. Monitoring and control that all specification and contract agreement are well executed and coordinated. Reviewing all site drawing prior to implementation to ensure that plan and site condition are coincided to prevent delays in project execution. Discuss all possible problems and recommend a solution to the owner’s representative for approval prior to implementation. Attending weekly and special project site meeting for site progress reports and site issues.
Project Involvement: PHILIPPINE SPORTS COMPLEX
Phillippine Arena, Philippine Sports Center & Philippine Sports Stadium
( Ciudad de Victoria, Bocaue & Sta. Maria, Bulacan, October 2012- June 2014 )
Responsible for reviewing of site documentation such as constructor’s billing, evaluation of 3rd party engineering design documents, and provision of technical input to the project and when required. Also in charge of the daily management, operational projects including meeting for project work schedules.
Carrying out pre-inspections and final inspections. Review and evaluate of methodologies submitted by contractors prior to approval and implementation. Arrange the planning and scheduling of work.Directing tasks to a multi-disciplined team.
Oversee all required and necessary testing to ensure the quality of materials to be use and used are pass on the set standard by the designers.
Project Involvement:
I. KING ABDULLA PETROLEUM STUDIES AND RESEARCH CENTER
Riyadh, Saudi Arabia. August 15, 2010 – May 5, 2011
Designation: QA/QC Engineer
II. GLOBAL PIPE COMPANY PROJECT – Civil and PEB Metal Works
Jubail KSA, May 6, 2011 – September 15, 2012
Designation: Civil Engineer
Main responsibilities:
– As QA/QC Engineer
Responsible for reviewing the drawing issued by owner’s representative and raised technical queries if there’s any conflict with the plan and site actual situation. Managed the site in terms of quality of works or workmanship that must be base on the Saudi Aramco Standards. Preparing and managing the pouring activities as per daily and weekly pouring forecast. Preparing BBS ( bar bending schedule ) for structural members and seek approval from owner’s representative prior to implementation. Conduct pre-inspection in every activity to ensure that the item to be inspected by owner’s representative will pass on the set standard as per contract agreement.
-As Civil Engineer
Managed the site in terms of proper execution, monitoring, and control to make a progressive accomplishment. Prepares bar bending schedule for every structural member based on Royal Commission standard. Primary secure the safety and health of the workforce during execution of all activities. Reviewing the drawing issued by the client and raised technical queries if there’s any conflict or differences between the plan and actual site condition. Attending weekly and monthly coordination meeting with the client in order to properly coordinate any problems and Owner’s supply materials schedules. Quantifying materials to be used for the activities on a weekly basis. Prepares monthly billing with complete justification. Prepares three weeks look ahead schedule.
Project Involvement: Doha North Sewerage Treatment and Associated Works
Shaft Handle:
T6/M3 – T7 (530 meters distance, 1800 mm Dia. ) – April 26, 2009 – June 28, 2009
T2/2/M2 – T2/2/M3(125 meters distance, 1000 mm Dia.) – June 29, 2009 – August 05, 2009 T1/M2 – T1 ( 645 meter distance, 2400 mm Dia.) – October 03, 2009 – December 17, 2009 T11 ( 540 meter distance, 1400 mm Dia.) – December 18, 2009 – February 15, 2010
T12/M1 ( 296 meter distance, 1400 mm Dia.) – February 16, 2010 – April 25, 2010
Main Responsibilities:
Managed, monitoring and control the project site.
Quantifying materials to be used as per project is concern
Controlling the quality of works base on the client satisfaction
Prepare Plan layout aided w/ AutoCAD application base on site condition
Location : Office ( Planning and Procurement Department )
Duration : August 06, 2009 – October 02, 2009
Responsibilities:
Monitoring daily material requisitions
Coordinate for materials delivery and checking materials quality and quantity
Preparing reports on daily and monthly basis as per site’s consumptions
Project Involvement: Canyon Ranch
Project Handle:
I. Construction of 12 Units Stanford 3 model
II. Construction of 29 Units of Town House casitas model
III. Construction of 108m length retaining structures
IV. Construction of 12 units duplex Napa model
V. Construction of 156m length road
VI. Construction of 5 units Fremont model
Responsible for Project evaluation/supervision. Compiling, checking and approving billing request evaluation as per contract agreement and as per actual accomplishments.
Quantifying materials to be used as per project is a concern. Controlling the quality of product base on the client satisfaction. Prepares Plan layout aided w/ AutoCAD application base on site condition.
Project Involvement: Proposed Rotisserie Stores (35 Stores)
Responsibilities:
Project evaluation/supervision
Prepares Billing request as per Project agreements and as per actual construction.
Preparing Architectural layout aided w/ AutoCAD application
Quantifying materials to be used as per project is concern
Controlling the quality of product base on the client satisfaction
Preparing Materials and Cost Estimate
Evaluating Project Contract
Project Involvement: Proposed Two Storey Residential w/ basement
Responsibilities:
Project evaluation/supervision
Preparing Billing request as per Project agreements and as per actual accomplishment
Controlling the quality of product base on the client satisfaction
Preparing Materials and Cost Estimate
Evaluating Project Contract
Preparing Pert CPM, S-Curve and Labor statement
Structural designing aided w/ STAAD.Pro2004 application
Preparing Architectural layout aided w/ AutoCAD application
Handling Workers/Workers Evaluator
Project Involvement: NUSA DUA Farm Estate
Projects handle:
I. Construction of Snack Kiosk
II. Construction of Guard Outpost
III. Construction of Green House
IV. Construction of Perimeter Fence
V. Construction of Meditation Room
VI. Construction of Marketing Office
VII. Construction of Admin office
VIII. Construction of Staff Office
Responsibilities:
Coordinating some site issues and problem encounter by the contractor’s handling the project
Prepares reports on issues and status of the project handled
Controlling the quality of product base on the client satisfaction
Quantifying materials to be used as per project is concern
Billing request evaluation as per contract agreement and as per actual accomplishments
Project evaluation/supervision
Project Involvement:
I. Construction of Home for Special Children
II. Construction of Dormitory
Responsibilities:
Project evaluation/supervision
Conducts Quantity Survey and Conducting Quality Control
Prepares Materials and Cost Estimate
Evaluates Project Contract
Preparing Pert CPM, S-Curve and Labor statement
Structural designing aided w/ STAAD.Pro2004 application
Making Architectural layout aided w/ AutoCAD application