Civil Engineer with total 25 years of experience in supervision and management of pipe laying works including Micro Tunneling, excavation, installation of house service connections, air release valves, blow offs, fire hydrants and district meters, construction of chambers, road and drainage construction, land development and other kinds of civil works.
1. Supervises and monitors the following activities
Pipe laying of Ductile Pipe ( 100mm dia. up to 400mmdia.)
Trench Excavation
Shut down from existing to proposed pipe
Installation of House Service Connections, Air Release Valves, Blow Offs, Fire Hydrants, and District Meters
Construction of all kind of Chamber
2. Ensures that the works are constructed strictly in accordance with the Contract specifications and accompanying drawings.
3. Monitors the adequacy of the equipment and human resource (manpower) requirements
4. Estimates the materials requirements
5. Coordinate to Kahramaa inspector for the inspection of the completed work and the schedule of shut down
1. Supervises and monitors the following activities
Pipe laying of Ductile Pipe ( 100mm dia. up to 400mmdia.)
Pipe laying of HDPE pipe (125mm dia. To 500mmdia.)
Trench Excavation
Shut down from existing to proposed pipe
Installation of House Service Connections, Air Release Valves, Blow Offs, Fire Hydrants, and District Meters
Construction of all kind of Chamber
2. Ensures that the works are constructed strictly in accordance with the Contract specifications and accompanying drawings.
3. Monitors the adequacy of the equipment and human resource (manpower) requirements
4. Estimates the materials requirements
5. Prepares the Detail for the shut down and daily accomplishment reports
6. Coordinate to Kahramaa inspector for the inspection of the completed work and the schedule of shut down
7. Conduct trial hole for all underground utilities prior to start excavation for pipe laying and micro tunneling
1. Supervises and monitors the following activities
Pipe laying of Ductile Pipe ( 200mm dia. up to 600mmdia.)
Trench Excavation
Shut down from existing to proposed pipe
Installation of House Service Connections, Air Release Valves, Blow Offs, Fire Hydrants, and District Meters
Construction of District Meter and Sluice Valve Chamber
2. Ensures that the works are constructed strictly in accordance with the Contract specifications and accompanying drawings.
3. Monitors the adequacy of the equipment and human resource (manpower) requirements
4. Estimates the materials requirements
5. Check the inside barrel of the pipes free from dirt and other extraneous materials (including sand bedding and soils) during the jointing and the laying process, and after the pipes have been laid.
6. Prepares daily accomplishment reports
1. Supervised and monitored the following activities
Pipe laying of PVC, HDPE, GSP, Steel Pipe, Cast Iron Pipe & Ductile Pipe
Interconnection from existing to proposed pipe
Installation of House Service Connection, Air Release Valve, Blow Off, Fire Hydrant, In Line Booster Pump, District Meter & Pressure Release Valve
Construction Valve vault, Valve box and Manhole.
Construction of New Deepwell and elevated water tank.
2. A detailed knowledge of the Contract specifications and accompanying drawings. (A thorough knowledge of the above documents is essential to ensure that the works are constructed in strict accordance with the Contract.)
3. Monitored the adequacy of the equipment and operators of the contractor.
4. Monitored the adequacy of the daily human resource (manpower) requirements of the Contractor.
5. Monitored the adequacy of the daily material requirement of the Contractor.
6. Ensured that the Contractor maintains the inside barrel of the pipes free from dirt and other extraneous materials (including sand bedding and soils)-both during the jointing and the laying process, and after the pipes have been laid.
7. Prepared Time extension and Variation order of the contractor
8. Checked the safety standard requirement before working if the contractor complies.
9. Prepared daily accomplishment report of the contractor and S-Curve.
10. Reviewed and evaluated the progress billing of the contractor.
1. Supervised and monitored of the following activities:
Pipe laying of 400mmØ SP and1200mmØSP
Pipe Jacking of 1200mmØSP
Valve Replacement
Interconnection from existing 1050mmØ SP to proposed 1200mmØ SP
Construction of manhole and valve vault.
2. Notified the contractor when it failed to comply with any provisions of the contract including provision of a safe and healthy working environment for staff and workers.
4. Checked the workmanship of all aspects of the works.
5. Monitored the adequacy of the equipment and operators of the contractor.
6. Monitored the adequacy of the daily human resource (manpower) requirements of the
Contractor.
7. Monitored the adequacy of the daily material requirement of the Contractor.
8. Ensured that the Contractor maintains the inside barrel of the pipes free from dirt and other
extraneous materials (including sand bedding and soils)-both during the jointing and the
9. Conducted dye penetration test.
1. Supervised and monitored of the following activities:
Land Development of Dolmar Hills Subdivision @ Marilao Bulacan
Construction of Road( Department of Public Works and High Ways Project)
Pipe laying
Interconnection from existing to proposed
Construction of valve vault and manhole.
Construction of roads and drainage.
2. Monitored the adequacy of manpower, materials and equipment needed.
3. Prepared the material requirement for testing needed
4. Prepared the weekly accomplishment and progress billing.
5. Conducted field density test.
1. Prepared daily accomplishment reports
2. Monitored the adequacy of the daily manpower, materials and equipment
needed.
3. Supervised and monitored pipe laying and interconnection
1. Supervised and monitored of the following activities:
Pipe laying, looping, valve replacement, and interconnection
Installation of new meter assembly and meter relocation
Construction of district meter and manhole.
2. Monitored the adequacy of the daily manpower, materials and equipment
needed.